Bridge Power Solution w/ Turbine Power Generation
Power: Two 60MW power blocks for a 120MW total @ 13.47kV - 13.8kV
Duration: 7 months
Setup Time: 2 1/2 Weeks
Application: Prime Power
Location: Gulf Coast Louisiana
Equipment: Solar SMT-60, Solar T-60, Siemens SGT-40
A Petrochemical facility in Louisiana faced a crucial challenge during the commissioning phase of their permanent gas turbines. Recognizing the need for reliable bridge power to facilitate this intricate process, they turned to Distributed Power Solutions. Our collaboration not only assisted in the commissioning of vital facility components but also played a pivotal role in sustaining overall plant operations throughout this critical period.
From the moment the initial project discussions commenced to the swift mobilization, a mere span of eight weeks elapsed. Remarkably, within just 2 ½ weeks of mobilization, we had both sites up and running smoothly, ensuring seamless power support and operational continuity for the facility's commissioning phase. This accomplishment stands as a testament to our dedication, expertise, and efficiency in delivering timely power solutions tailored to our clients' specific needs.